GOV.UK is often the example that the public sector can build digital services fast and well. That is true. But the interesting part is what happened next, and that the team wrote about it themselves.

By Fawzi Aiboud Nygren, Dalanovum · Published ·

Short answerGOV.UK replaced the websites of 1,882 government organisations in three years, but built up technical debt on the way. In 2017 the team changed how it worked: missions of at most three months, measurement in numbers, a week between missions and sustainable technology.

Fast, and at a cost

GOV.UK launched in 2012. A little over a year later, 24 departments and the content of 330 organisations were on the platform. By 2015 the site had replaced the websites of 1,882 government organisations.

The figure 1,882 counts organisations, not websites. That difference often disappears when the story is retold.

The team writes that the speed had a price. They had built up a lot of technical debt: solutions that were fast to build but could cause problems later. The number of people involved in the programme also varied over its course.1

Four problems, four new principles

In early 2017 the team saw four problems that affected delivery:

The answer was four principles:

  1. At most three months per mission. Every third month the question had to be asked for real: should we go on with this?
  2. Measure in numbers. Every team had to show that the three months had been a good investment.
  3. A firebreak between missions. A week between each mission, for learning and for changing teams.
  4. Build to last. Reduce the technical debt.
About twenty small browser windows in an untidy pile, some cracked, pour into one single purple window. On the right stand three equal blocks with a gap between each.
First everything was gathered in one place. Then the work was split into missions of at most three months, with a week between them.

What did they learn?

With 168 people spread across 24 teams, the programme was hard to steer as a whole. The team split the work into a few goals, each with 3 to 5 missions and about 40 people.

The three-month rule did not hold for everything. Some work needs more time, or teams start to prioritise the wrong things. They now tried missions of 6, 12, 18 or 24 weeks. The decision point mattered, not the exact length.

And the sentence most worth quoting: if they did it again, they would put a lot of effort into building and measuring a baseline from the start, and make the change only once the measurement was in place.

What can a municipality take from it?

The question is rarely how fast a new website can launch. The question is how the information, the ways of working and the responsibility hold when the organisation changes.

Common questions

How many websites did GOV.UK replace?

By 2015 GOV.UK had replaced the websites of 1,882 government organisations.

The figure counts organisations, not websites. Many organisations had more than one website.

What is technical debt?

Technical debt is solutions that are fast to build but cost time and money to fix later.

It is not always wrong. It becomes a problem when nobody owns it and nobody plans to pay it off.

Why missions of at most three months?

Every third month the team has to ask whether the work should go on, and show in numbers what it gave.

GOV.UK later found that not all work fits in three months. The decision point mattered, not the exact length.

Sources 1

  1. Government Digital Service: GOV.UK: a journey in scaling agile, 26 April 2018. ↑