The system is live. But did the work get better?

A go-live is a delivery. The benefit still has to be shown. It sounds obvious, but that is where many public IT projects stop counting.

By Fawzi Aiboud Nygren, Dalanovum · Published ·

Short answerNo, a system in place does not mean the work got better. Go-live is the first of five steps: delivery, adoption, use, effect and realised benefit. The benefit can only be shown if there was a baseline, a measure per goal and an owner in the organisation before the system was built.

Five things that are often mixed up

When a new system goes live, the project is usually counted as done. But go-live is only the first of five steps:

  1. Delivery. The system exists and works technically.
  2. Adoption. Staff have had training and new routines.
  3. Use. The system is used in daily work, not only when it has to be.
  4. Effect. Something measurable has changed: shorter handling, fewer errors, less double work.
  5. Realised benefit. The effect is large enough to carry the cost, and someone is responsible for keeping it.
A staircase of five steps. The lowest step, with a computer and a check mark, is strong purple. The steps above fade, and the top one with a flag can hardly be seen.
Go-live is the first step. The colour fades with every step that is seldom followed up.

Follow-up often stops at step one or two. That is where the budget ends and the project team moves on to the next assignment.

What does Digg see in Sweden's central government agencies?

The Swedish Agency for Digital Government, Digg, follows up every year how the central government agencies digitalise. In its report of 14 August 2026, Digg writes that the agencies' ability to focus development on the expected benefit, and to realise the benefit of completed work systematically, needs to be strengthened further.1

This applies to central government agencies. Municipalities and regions are not part of the survey, so the conclusion cannot be carried over to them. Parts 3 and 4 look at two large regional roll-outs.

The question to ask after every go-live

Which outcomes were measured after go-live, and compared with what? To answer, three things are needed, and they must exist before the system is built:

The GOV.UK team in the United Kingdom writes that, if they could redo their change work, they would have invested heavily in measuring and setting a baseline from the start.2 It is an unusually honest sentence from an organisation that is often held up as a model.

The parts of the series

None of the articles is a verdict on individual people. They are about how decisions are made and what is measured, because that is where the next project can do it differently.

Frequently asked questions

What is benefits realisation?

Benefits realisation is the work of making sure an investment gives the effect it was decided for.

It starts before the project, with a baseline and measures, and continues after the system is in use.

When is an IT project done?

An IT project is done when the effect has been measured and someone in the organisation owns it, not when the system goes live.

Go-live is step one of five: delivery, adoption, use, effect and realised benefit.

What should be measured before a new system?

Measure how things work today: case time, error rate and cost.

Without that baseline, there is no way to show that the new system made a difference.

Does Digg's conclusion apply to municipalities and regions?

No, Digg's follow-up covers central government agencies.

Municipalities and regions are not part of the survey.

Sources 2

  1. Digg (Swedish Agency for Digital Government): Follow-up of the digitalisation of central government agencies 2025, 14 August 2026, in Swedish. ↑
  2. Government Digital Service: GOV.UK: a journey in scaling agile, 26 April 2018. ↑